The Pyebridge Project (“Pybridge”) was acquired by MED in August 2021 as a fully operational gas powered 9 MW Reserve Power site and has continued in operation since acquisition.  Pyebridge is located in Derbyshire.

Mast Energy Developments

The Bordesley Project (“Bordesley”) is the first Reserve Power (“RP”) project acquired by MED and is now in the construction stage with an anticipated completion and in steady-state production by Q2 2022. Bordesley is a 5 MW gas powered RP site  extendable to 19.12 MW located in Central Birmingham.

Mast Energy Developments

The Rochdale Project (“Rochdale) is a 4.4 MW capacity near shovel ready Reserve Power (“RP”) site for the installation of gas-powered Reserve Power plant, acquired by MED in October 2021.  Rochdale  is located in the West Midlands.